DESCRIPTION
Installation and commissioning a 5.4-megawatt run of river hydroelectric project.
OUR ROLE
North Construction successfully planned, fused, and installed a 30” HDPE penstock and commissioned the intake and powerhouse structures in a remote environment. Through coordinated execution, the team completed instream works to divert creek flows into a newly constructed channel, enabling power production. The work was delivered safely, on schedule, and within budget.
PROJECT HIGHLIGHTS
- Site access and safety for a remote project
- Fusing large diameter HDPE pipe
- Installation of a buried HDPE penstock and power cable
- Installation and use for construction of highline cable crane
- Installation of surface mounted penstock and power cable
- Completion of the powerhouse and intake structures
LOCATION AND YEAR
Whistler, BC, Canada (2021-2022)
CLIENT
Concord Green Energy
CATEGORY
Hydroelectric, Creek Diversion