Mount Seymour High Voltage Replacement

DESCRIPTION

Complete replacement of Mt Seymour’s high voltage line from Lodge chair to top of Mystery chair.

OUR ROLE

We commenced the installation of six high voltage cables, stretching from the Mt Seymour parking lot to the top of the Mystery chair (~2000m). North Construction collaborated closely with Mt Seymour electricians to ensure the project was completed on time and within budget. 

PROJECT HIGHLIGHTS

  • Efficiently managed steep machine and rock truck access. 
  • Collaborated closely with QEP to address ESC issues
  • Successfully commissioned the entire electrical line without faults. 
  • Effectively managed hikers and pedestrians
  • Skillfully handled existing unmarked utilities 

LOCATION AND YEAR

North Vancouver, BC, Canada (2022)

CLIENT

Mt. Seymour Resort