DESCRIPTION
Removal and installation of a new quad chairlift at Cypress Mountain Resort
OUR ROLE
North Construction provided demolition, excavation, concrete forming and placing for new tower footings and chairlift terminals. Due to the mountainous terrain construction materials and concrete were placed by helicopter. Tower footing excavation was completed with a combination of modified conventional excavator as well as spider excavator.
PROJECT HIGHLIGHTS
- Modeling and Design work
- Survey and Layout
- Steep Terrain Excavation
- Removal of the old chair lift footings, towers and
- terminals
- Forming mixing and placing lift line concrete
- Logistics support for tower and terminal installation
LOCATION
West Vancouver, Canada
CLIENT
Boyne Resorts